Case Study:

Discrepant Design

Project Analysis :

Challenges :

1. Suppliers' ability to provide when the design organization...
- 1a. Incomplete design
- 1b. Not working to the process
2. Supplier was not aware how to communicate concerns

Solution :

1. Educated supplier's Project, Quality, and Engineering Managers of the communication tools available to them
2. Worked as the liaison between engineering departments to formalize manufacturers capabilities
3. Placed Manufacturing Hold on the project until Engineering and the PM instituted design changes in drawings/specifications and contractually issued to supplier.

Impact :

1. Engineering finalized & contractually issued 17 design drawing/specifications
2. Resulted in a savings of over $108,000 in design changes
3. Return on Investment: 980%